Grapevine Infiniti Dealership Construction Update

Our project is coming along well and a lot has happened in the last month

South parking concrete is complete

North parking concrete has started on the front and around the corner

The Feature Glass Wall structure is complete and glass is being sized

Glass is being installed on the Pre-Owned offices

The stucco portion of the building is complete and painted

Stone is being added to the Pre-Owned offices

Soon the building will be in the dry and interior painting will begin!

20141103